Vineyard Wind 1, the first and so far only offshore wind project built for Massachusetts under a 2016 clean energy law, got fully up to speed late last month just as another regional resource came fully online.

Massachusetts utility companies selected Vineyard Wind 1 with input from the Baker administration to fulfill part of a 2016 clean energy law, and it is likely to be the only Massachusetts offshore wind project to become a reality this decade. Subsequently selected projects ran into headwinds that developers determined threatened their project financing and resulted in the termination of those contracts. Additional planned procurements have repeatedly been delayed.

The first electrons from the roughly 800 megawatt project about 15 miles south of Martha’s Vineyard began flowing in early 2024, but one of the project’s massive blades shattered in the summer of 2024, bringing operations to a halt and prompting investigations. Partial power production had resumed by January 2025.

Support for GBH is provided by:

“On Thursday, October 29, Vineyard Wind 1 reached full commercial operations, further strengthening New England’s energy supply,” Vineyard Wind spokesman Craig Gilvarg wrote in an email, confirming news that had previously been reported.

Around 12:45 p.m. Tuesday, all sources of wind power were providing about 856 MW of power to the New England grid, according to real-time data from grid operator ISO New England. Wind power was 45% of all the renewable power on the grid at the time, or about 7.3% of all power available.

On Nov. 5, the global offshore wind developer Ørsted announced its financial results, highlighting the start of commercial operations at its Revolution Wind offshore wind energy project off Rhode Island as well as an offshore wind farm in Germany. Ørsted also said it reached key milestones in offshore wind construction projects in Taiwan, Poland and the U.K., with its construction portfolio progressing “according to schedule and on budget.”

The Denmark-based company said it completed the installation of remaining wind turbines at the 704 MW Revolution Wind project, which benefits Rhode Island and Connecticut.

“In October the project achieved commercial operations under its offtake contracts with utilities in the states of Connecticut and Rhode Island,” Ørsted said, adding that its 2,852 MW Hornsea 3 project in the United Kingdom is “the world’s largest offshore wind farm project.”

Support for GBH is provided by:

Gov. Maura Healey called Vineyard Wind 1's full operation “a major milestone for the American offshore wind industry and an important boost to our grid’s reliability this winter.”

“With the project at full commercial operation alongside Revolution Wind, offshore wind will bring down the price of electricity even further in New England. This is a Massachusetts industry, bringing thousands of good-paying union jobs and investment to our port communities,” Healey said.

Rhode Island Gov. Dan McKee called Revolution Wind “a major win for Rhode Island’s workforce and our state’s energy future.”

“Helping bring this project to completion has been a highlight of my administration, from the good-paying jobs it has created for hardworking union workers to our successful work to protect it from interference by the Trump Administration,” McKee said. “This project reflects our commitment to an all-of-the-above energy strategy and to supporting investments that create opportunities for Rhode Islanders.”

In the U.S., Ørsted has installed all wind turbine foundations at its 924 MW Sunrise Wind project, where commercial operations are planned for 2027, and started construction of a 200 MW Blackwater Solar project. Sunrise Wind is located between Martha’s Vineyard and Montauk Point and will serve power users in New York.

The company said it is dealing with impacts of rising interest rates and tariff costs.

The Conservation Law Foundation noted that South Fork Wind off the coast of Block Island powers about 70,000 homes and businesses on Long Island with a dozen turbines, and Revolution Wind’s 65 turbines can play a key role in delivering power to meet wintertime energy demands.

“Offshore wind projects like Revolution Wind are clear examples of what we can achieve when we invest in homegrown, clean energy,” Anxhela Mile, a CLF staff attorney, said.

That Vineyard Wind 1 would be constructed and become operational has not always been a sure thing. Project developers originally planned to close financing on the project and begin onshore construction work in 2019, put the first turbine into the seabed in 2021 and begin generating electricity in 2022.

But the Trump administration in the summer of 2019 decided to undertake a broad study of the potential impacts of offshore wind projects planned up and down the East Coast, holding up a key permit approval for Vineyard Wind 1. Vineyard Wind announced on Dec. 1 of that year that it was pulling its project out of the federal review pipeline. The Trump administration declared the federal review of the project “terminated.”

Less than a month into Joe Biden’s presidency, in February 2021, the federal government resumed the review of the Vineyard Wind 1 project from the point at which the developer withdrew it. By May of 2021, the Biden administration had approved the project’s construction and operations plan and cleared the way for construction to begin.

State officials once said Massachusetts needed to be bringing about 1 gigawatt of new offshore wind power online each year in the 2030s to meet its binding midcentury decarbonization targets. But there are no additional offshore wind farms in the state’s pipeline and the process to get more projects lined up has been delayed at least six times, putting it more than two and a half years behind schedule.